drivers and commuters

Click the tabs below to see the impacts for drivers in certain areas of the project.
​
Scroll down to see general information.

I-25 LANE SHIFT IMPACTS
​
Beginning the evening of June 19, a traffic shift will occur on the northbound Pan American Frontage Road and the northbound I-25 off-ramp from Comanche Road. To facilitate the lane shift, crews will implement nighttime full lane closures and ramp closures on I-25 Frontage Road between 8 p.m. and 6 a.m. starting on the evening of June 19 through the weekend.
The new traffic pattern will help prepare for an I-25 mainline shift later this month.
As early as June 30, crews will shift travel lanes on northbound and southbound I-25 to the outside lanes to begin work on the inside lanes. There will be three travel lanes open in each direction between Comanche Road and Montgomery Boulevard during the daytime. Crews will implement nighttime lane closures on I-25 between 8 p.m. and 6 a.m. to facilitate the shift, which may take several days to complete.
The new traffic pattern will shift from the current lanes to the newly constructed lanes on I-25 beginning Phase 2 of the project!
The speed limit in the work zone has been reduced to 55 mph. Please slow down and use caution.
Click here to see a detailed map of the lane shift. ​​​​​​​​​​​​​​​​​​​​​​

​​​​TYPICAL OVERNIGHT I-25 LANE CLOSURES DETAILS
​
​During the week, up to two travel lanes on I-25 will close at 8 p.m. each night and reopen by 6 a.m. each morning, in time for the morning commute. Crews will close one lane at 8 p.m. and another lane at 10 p.m., keeping one lane open in each direction. All lanes will be reopened by 6 a.m. each morning.
​
During the weekend, travel lanes on I-25 will close at 10 p.m. each night and reopen by 9 a.m. each morning. Crews will close one lane at 10 p.m. and another lane at 11 p.m., keeping one lane open in each direction. All lanes will be reopened by 9 a.m. each morning.
​​GENERAL INFORMATION
Lane closures on I-25, ramps, frontage roads, and Montgomery Boulevard will usually happen during off-peak times (outside of rush hours and on weekends).
​
Drivers can expect uneven pavement on the roadway and should use caution while traveling through the work zone.
​
​​​​​Construction will occur both day and night, up to seven days a week. Our team will keep this page up to date with specific activities that may impact you.